British Steel Corp v Cleveland Bridge and Engineering Co Ltd : ウィキペディア英語版 | British Steel Corp v Cleveland Bridge and Engineering Co Ltd
''British Steel Corp v Cleveland Bridge and Engineering Co Ltd'' () 1 All ER 504 is an English contract law case concerning agreement. ==Facts== Steel nodes delivered to defendants after letter of intent to buy, but no formal contract had been concluded because the claimants refused to use the defendants’ terms, and negotiations took so long. No agreement was reached on progress payments and liability for late delivery, and defendants refused to pay because of lateness and nodes coming out of sequence. They had, however, been delivered.